NC
Norm Construction
AI Demo
Back to Portfolio

The Davis Island Historic

At Risk

227 E Davis Blvd, Tampa, FL 33606

1926 Mediterranean Revival · PM: Jimmy Chen · 800 sqft

Contract Value
$340,000
Progress
43%
Schedule
5d behind
CO Exposure
$52,600

Construction Phases

MEP Rough-In

2026-01-132026-02-21

60% completein-progress
Milestones
Full re-pipe (copper to PEX)2026-01-24
Full rewire (K&T removal)2026-02-07
HVAC ductwork (addition)2026-02-10
200A→400A service upgrade2026-02-14
MEP rough inspection2026-02-21
Costs
Plumbing (re-pipe)$17,200
Budget: $18,000
Electrical (full rewire)$19,500
Budget: $22,000
400A Service Upgrade$0
HVAC$8,200
Budget: $14,000
Total$44,900 / $54,000
Subcontractors
Sunshine Plumbing
Gulfcoast Electric
Comfort Zone HVAC
Issues
400A service upgrade pending TECO coordination — 2-week lead time for transformer
Architect's RFI response expanded electrical scope by $14,600 — CO pending owner approval
Documents
RFI-003: Electrical scope clarification2026-01-18
TECO service upgrade application2026-01-25

Permits

Number Type Status
BLD-2025-06724 Building Permit — Addition & Renovation approved
HPC-2025-00341 Historic Preservation Certificate of Appropriateness
Barrel tile roof, stucco finish, window proportions must match existing Mediterranean Revival character
approved
PLM-2025-04102 Plumbing Permit — Full Re-pipe approved
ELE-2025-06219 Electrical Permit — Full Rewire approved
ELE-2025-08441 Electrical Permit — 400A Service Upgrade
Pending TECO transformer upgrade coordination. 2-week lead time after approval.
pending
MEC-2025-03892 Mechanical Permit — HVAC approved

Inspections

Type Date Result
Foundation 2025-11-12 passed
Framing 2025-12-20 passed
Roof Deck / Nail Pattern 2025-12-28 passed
Plumbing Rough (re-pipe) 2026-01-28 passed
Electrical Rough (rewire)
400A panel location must be confirmed before final. Conditional pass for rough.
2026-02-10 conditional
MEP Rough (combined) 2026-02-21 scheduled

Cost Breakdown

Category Budgeted Actual Committed Variance
Design & Engineering $18,000 $18,000 $18,000 $0
Demolition & Abatement $12,000 $20,500 $20,500 -$8,500
Foundation & Concrete $32,000 $31,500 $31,500 $500
Framing & Carpentry $38,000 $37,200 $37,200 $800
Roofing $22,000 $21,800 $21,800 $200
Exterior / Stucco $16,000 $14,500 $16,000 $0
Plumbing (incl. re-pipe) $18,000 $17,200 $18,000 $0
Electrical (incl. rewire + 400A) $22,000 $19,500 $36,600 -$14,600
HVAC $14,000 $8,200 $14,000 $0
Finishes & Millwork $78,500 $0 $62,000 $16,500
Total $270,500 $188,400 $275,600 -$5,100

Weather Impact

Tropical Storm Warning 2025-11-12

Foundation pour delayed 2 days. Crew stood down per FBC §1609 wind provisions.

2d lost
Cold Front (38°F overnight) 2025-12-15

Concrete curing blankets required for addition slab. No schedule impact.

No delay
Heavy Rain (3.2" in 4hrs) 2026-01-20

Roofing work paused 1 day. Interior work unaffected due to dry-in.

1d lost

Subcontractor Directory

Tampa Bay Demo Pros
Demolition
complete
Mike Torres
(813) 555-0142
SafeAir Environmental
Asbestos Abatement
complete
Lisa Park
(813) 555-0188
Hillsborough Concrete
Foundation & Concrete
complete
Tony Russo
(813) 555-0256
Bay Area Framing
Framing
complete
Carlos Vega
(813) 555-0198
Tampa Roofing Co
Roofing
complete
Dan O'Brien
(813) 555-0334
Classic Stucco & Stone
Exterior Stucco
complete
Marco Diaz
(813) 555-0391
Sunshine Plumbing
Plumbing
active
Pete Hernandez
(813) 555-0223
Gulfcoast Electric
Electrical
active
Steve Kim
(813) 555-0317
Comfort Zone HVAC
HVAC
active
Ray Nguyen
(813) 555-0478
Back to Portfolio