The Westchase Kitchen

On Track

12438 Countryway Blvd, Tampa, FL 33626

2001 Florida Tract Home · PM: Dani Reyes · 280 sqft

Contract Value
$78,000
Progress
35%
Schedule
1d ahead
CO Exposure
$0

Construction Phases

MEP Rough-In

2026-02-102026-02-28

60% completein-progress
Milestones
Plumbing relocation (sink to island)2026-02-14
Electrical rough-in (island, undercab, hood)2026-02-21
Gas line for range2026-02-25
MEP inspection2026-02-28
Costs
Plumbing$4,200
Budget: $5,500
Electrical$4,800
Budget: $6,000
Total$9,000 / $11,500
Subcontractors
Sunshine Plumbing
Gulfcoast Electric

Permits

Number Type Status
BLD-2026-00312 Building Permit — Kitchen Remodel approved
PLM-2026-00145 Plumbing Permit approved
ELE-2026-00234 Electrical Permit approved

Inspections

Type Date Result
Framing / Structural
LVL beam connection approved.
2026-02-07 passed
Plumbing Rough 2026-02-17 passed
Electrical Rough 2026-02-24 scheduled

Cost Breakdown

Category Budgeted Actual Committed Variance
Design $2,500 $2,200 $2,200 $300
Demo & Structural $8,000 $8,000 $8,000 $0
Plumbing $5,500 $4,200 $5,500 $0
Electrical $6,000 $4,800 $6,000 $0
Finishes & Install $52,800 $0 $38,000 $14,800
Punch $1,200 $0 $0 $1,200
Total $76,000 $19,200 $59,700 $16,300

Subcontractor Directory

Tampa Bay Demo Pros
Demolition
complete
Mike Torres
(813) 555-0142
Bay Area Framing
Framing
complete
Carlos Vega
(813) 555-0198
Sunshine Plumbing
Plumbing
active
Pete Hernandez
(813) 555-0223
Gulfcoast Electric
Electrical
active
Steve Kim
(813) 555-0317
Tampa Custom Cabinets
Cabinetry
scheduled
Dave Kowalski
(813) 555-0634